Community Hub/Community Centre Annex
- jjbartels
- Apr 5, 2024
- 1 min read
Perimeter security fencing has gone up around the site where the MPB Community buildings will be constructed on Club Avenue at MPB. Works will soon commence on the construction of these much awaited for community facilities.
The contractors undertaking the project are on track with their timeframe projections as previously advised and are below. The Community Reference Group and Stakeholders involved with the project are scheduled to meet in the next couple of weeks to view plans and to be given a full update on the development. I will also share information on Stages 2 & 3 of the MPB Masterplan after the meeting on the 18th April.
Exciting times ahead, watch this space!
𝓚𝓮𝔂 𝓓𝓪𝓽𝓮𝓼 𝓪𝓼 𝓯𝓸𝓵𝓵𝓸𝔀𝓼:
- 80% 𝓭𝓮𝓽𝓪𝓲𝓵𝓮𝓭 𝓭𝓮𝓼𝓲𝓰𝓷 𝓱𝓸𝓵𝓭 𝓹𝓸𝓲𝓷𝓽 𝓪𝓷𝓭 𝔀𝓸𝓻𝓴𝓼𝓱𝓸𝓹 15/03
- 𝓑𝓾𝓲𝓵𝓭𝓲𝓷𝓰 𝓪𝓹𝓹𝓻𝓸𝓿𝓪𝓵𝓼 29/03
- 100% 𝓭𝓮𝓽𝓪𝓲𝓵𝓮𝓭 𝓭𝓮𝓼𝓲𝓰𝓷, 𝓬𝓮𝓻𝓽𝓲𝓯𝓲𝓮𝓭 𝓘𝓕𝓒 𝓭𝓻𝓪𝔀𝓲𝓷𝓰𝓼 01/04
- 𝓒𝓸𝓷𝓼𝓽𝓻𝓾𝓬𝓽𝓲𝓸𝓷 𝓬𝓸𝓶𝓶𝓮𝓷𝓬𝓮𝓶𝓮𝓷𝓽 08/04
- 𝓟𝓻𝓪𝓬𝓽𝓲𝓬𝓪𝓵 𝓬𝓸𝓶𝓹𝓵𝓮𝓽𝓲𝓸𝓷 𝓪𝓻𝓸𝓾𝓷𝓭 23/09/2024.